On a utility-scale solar project, a module goes through many steps before it produces power. It is shipped, unloaded, stacked, moved to the block, lifted onto the tracker and clamped in place, and any of those steps can crack its glass or cells. Some damage is obvious the moment it happens. Other damage only shows up later, as a hot spot on a thermal scan or a string that underperforms during commissioning.
Each broken module then has to be recorded with its serial number and location, assigned to someone, replaced, re-tested and closed out. That can mean thousands of modules and several contractors. Digital inspection forms, module-level serial tracking and central defect management make this process much easier to control. This post covers:
the main types of module breakage and where they happen
the solar module testing methods that catch them
a step-by-step workflow for managing damage from discovery to closure
What Does Solar Module Testing Involve During Solar Project Construction?
Solar module testing is the process of checking the physical condition and electrical performance of modules at different stages of a project, from delivery to commissioning. PV module testing on site usually combines three kinds of work:
Visual inspection: checking modules for visible damage such as broken glass, bent frames, damaged junction boxes or torn backsheets.
Field or laboratory testing: methods such as electroluminescence (EL), IV curve tracing, flash testing and thermal imaging, which find damage and performance issues the eye can’t see.
Digital documentation: recording what was found, on which module, where and when.
Documentation is what connects a test result to a specific module. Without it, the team can’t replace the right module, re-test it or support a claim later.
Common Types of Module Breakage on Site
Module damage takes different forms. Each type needs to be recorded so the team can find it and act on it later.
Cracked and Shattered Glass
Broken front glass is the easiest damage to spot. A dropped module or an impact during handling can crack or shatter the glass. Because the damage is so visible, it can end up logged quickly as “broken module, Block 4”, without the serial number or exact position. That is enough to start a replacement. It isn’t enough to trace the module later for a supplier discussion or a warranty claim.
Micro Cracks and Cell Cracks
Micro cracks are fractures in the solar cells, usually invisible to the eye. Common causes are:
bending the module
stepping or kneeling on it
impacts during transport and installation
A cracked cell may show little power loss at first. Over time, temperature changes and mechanical load can widen the cracks and disconnect parts of the cell. That reduces output and can create hot spots. Because micro cracks can’t be seen, they are usually found through EL testing, or later through thermal imaging.
Frame, Junction Box and Backsheet Damage
Damage can also affect the parts around the cells:
A bent or cracked frame can weaken how the module is held on the tracker.
A damaged junction box or connector, or a scratched or torn backsheet, can expose live parts or let moisture in. That creates insulation and safety risks as well as performance issues.
These defects need different follow-up from glass and cell damage. Giving each one its own defect code in inspection forms avoids grouping everything under “broken module”.
Where Module Breakage Happens, from Delivery to Commissioning
Between the factory and commissioning, modules pass from the supplier to the logistics provider, to the site team at receiving, and then to the installation contractor. Who is responsible for a damaged module often depends on where the damage happened and what the contracts say. That’s why damage needs to be recorded at each handoff.
Transit, Unloading and Storage
Damage can start before modules reach the block. All of these can crack glass or cells:
rough handling in transport
careless unloading
incorrect stacking
storage on uneven ground or exposed to the weather
A damaged pallet or crushed packaging can be an early sign. Incoming inspections are the first chance to catch this damage. Photos of pallets and packaging on arrival, together with serial numbers recorded at receiving, give the team evidence of the condition the modules arrived in.
Installation and Pre-Handover Damage
During installation, modules are carried across the site, lifted onto trackers and clamped in place. Common causes of damage at this stage include:
stepping on modules
dropped modules
incorrect clamping
handling errors while carrying
accidental impacts from nearby equipment or tools
Inspections during installation, and again before commissioning, catch this damage while it is still easy to tell which crew and block were involved, and before it becomes a commissioning issue.
What Undetected Breakage Costs a Project
A broken module found late costs more to deal with than one found early. Late discovery can lead to:
Rework: modules are removed and replaced after the block has been signed off.
Replacement costs: the module itself, plus the labor to swap it.
Commissioning delays: damaged modules can affect string tests or punch list closure close to COD.
Potential generation losses: damaged modules may stay in service after energization.
Disputes over responsibility: without a record of when and where the damage happened, responsibility is harder to settle.
Finding damage early and documenting the corrective action keeps each of these costs smaller and easier to resolve.
Solar Module Testing Methods That Catch Breakage
Each testing method catches different damage at a different stage of the project.
Visual Inspection
Visual inspection is the first check, at receiving, during installation and before commissioning. It catches broken glass and damage to frames, junction boxes and backsheets. To be useful later, each finding needs a photo, the module serial number and the module’s position on site. Visual inspection can’t detect most cell cracks, so it needs to be paired with other methods.
Electroluminescence (EL) Testing
EL testing passes current through the module so the cells emit light, which a specialized camera captures. Cracks and inactive cell areas show up as dark lines or patches in the image. EL is the most direct way to find micro cracks, and it is usually done in low light or at night.
A practical approach is to EL test a sample of modules at receiving to check incoming quality. Testing can then be widened before commissioning.
IV Curve Tracing and Flash Testing
IV curve tracing measures the current and voltage output of an installed module or string and plots it as a curve. Comparing the curve with the expected result shows performance deviations. These can point to damaged modules, connection problems or other faults in the string. IV curve tracing is also a common way to confirm the cause of a defect found during a thermal inspection.
Flash testing measures a module’s output under controlled illumination from a solar simulator. It is usually done in a lab or a mobile test unit. It gives a precise power measurement to compare with the manufacturer’s rating, which helps assess modules suspected of damage.
Drone Thermal Imaging
Once the site is energized, a drone thermal survey can cover the whole site. Damaged cells and modules often run hotter than the modules around them, so they show up as hot spots in the infrared images.
Thermal imaging shows the effect of damage. The cause still has to be confirmed in the field, usually through a visual inspection or an IV curve trace on the affected module.
Method
What it catches
When to use it
Visual inspection
Broken glass, frame, junction box and backsheet damage
Receiving, installation, pre-commissioning
EL testing
Micro cracks and inactive cell areas
Sample at receiving, wider testing before commissioning
IV curve tracing
Performance deviations in modules and strings
Pre-commissioning, follow-up on suspected damage
Flash testing
Module power output compared with rated output
Sample checks in a lab or mobile test unit
Drone thermal imaging
Hot spots caused by damaged cells, modules and strings
After energization
When Should Solar Module Testing Be Done?
The methods above work best as an inspection schedule tied to project stages.
Receiving Inspection at Delivery
Receiving is the first chance to record the condition of modules before they go to the installation team. A receiving inspection should include a visual check, photos, a serial number scan and EL testing on a sample of modules. A short solar panel inspection checklist for receiving:
Check pallets and packaging for visible damage before unloading.
Photograph any damaged pallet or packaging before it is opened.
Record the serial numbers received against the delivery.
Visually check modules for broken glass and for frame and junction box damage.
EL test a sample of modules.
Record damaged or rejected modules separately, with photos and serial numbers.
Note the delivery date, the shipment and the inspector.
Installation Checks
During installation, spot checks catch handling and clamping damage while the work is recent. Each check should record the crew, the block and the module position. That way any damage found can be traced to where and when it happened, and who was working there.
Pre-Commissioning Baseline
Before commissioning, EL, IV curve and thermal results give the project a baseline of module condition at handover. Later discussions with suppliers or contractors, and future warranty claims, can refer back to this record. It needs to be complete and linked to individual modules.
Why Module Breakage Is Hard to Manage with Paper and Spreadsheets
On a utility-scale site with modules spread across many blocks, manual records fall behind quickly:
No serial-level traceability: a damage log that says “Block 6, Row 12” doesn’t say which module was broken or which one replaced it.
Photos without location details: photos shared in chat groups or saved on phones are hard to link to a specific module or position.
NCRs lost in email: non-conformance reports sent as attachments are hard to track to closure, and it is often unclear who owns the next step.
Delayed replacement tracking: it is hard to see which damaged modules have been replaced, which are waiting for stock and which still need re-testing.
Evidence that’s hard to retrieve: when a supplier or contractor asks for proof, the team has to pull photos, test results and serial numbers together from several places.
How to Manage Module Breakage with Digital Tools (Step by Step)
A digital workflow follows a damaged module from first identification to closure. The record stays attached to the module the whole way.
Step 1: Scan Module Serial Numbers During Receiving and Installation
Barcode scanning links each module’s serial number to where it sits on the site:
At receiving, serial numbers can be scanned against the delivery, so the team knows which modules arrived and can record any found damaged.
After installation, scanning teams record each serial number against its tracker and module position.
This gives every module a traceable record. When damage is found later, through a visual inspection, an EL test or a thermal scan, the team can identify the module and its serial number from its position. The same record then carries through inspections, replacements and claims.
Step 2: Record Module Damage with Drone Scans, Digital Checklists and Photographs
Adverse weather, such as a hailstorm or high winds, can damage modules across a partially or fully built site. A drone scan can cover the site quickly and show where modules have been damaged, so field teams know which blocks to inspect first. Depending on the extent of the damage, the drone's flight resolution can be adjusted, with finer resolution used when the damage is smaller and harder to spot. Visible damage such as broken glass shows up in the imagery, while cell cracks still need EL testing to confirm.
Field engineers can then use mobile inspection forms to record the damage, including:
the defect category
photos
the serial number and location
inspection details such as the date and the inspector
Fixed defect categories (cracked glass, cell cracks, frame, junction box, backsheet) keep records consistent across crews and blocks, so they are easier to filter and report on. Where the platform supports offline capture, forms can be filled in areas with weak signal and synced later.
Step 3: Raise an NCR or Punch List Item
Confirmed damage can be turned into an NCR or a punch list item with:
an assigned owner
a priority
a due date
the photos and inspection record attached
Site engineers, QA/QC teams and contractors then share one view of each open defect: who owns the next step, what evidence exists and what is overdue. Defects no longer have to be tracked in parallel across email threads and spreadsheets.
Step 4: Attach Inspection and Testing Results to the Module
Visual inspection photos, EL images, IV curve results and thermal inspection reports should all be linked to the serial number and location of the module they relate to. The team can then pull up a module’s full history in one place. That supports internal reviews, supplier discussions and warranty assessments.
Step 5: Replace, Re-Test, and Close the Defect
When a damaged module is replaced, the record should show:
the removal of the damaged module, with its serial number
the replacement module’s serial number, recorded at the same tracker and module position
the re-test or re-inspection result for the new module
photos of the completed replacement
Close the NCR or punch list item only after the corrective action has been verified. The installation record then matches what is on site, and the closed item carries its own evidence.
Step 6: Analyze Root Causes and Maintain Claim Records
When every defect is recorded the same way, teams can look for patterns, such as damage concentrated in:
one shipment or material batch
one block
one installation crew
These patterns help separate handling problems on site from quality issues at the source, so the team can act before the same issue repeats elsewhere.
The same records support supplier and solar module warranty claims. Photos, inspection reports, serial numbers and replacement records are all linked to each module, so the team doesn’t have to rebuild the evidence from scattered files.
Manual vs Digital Breakage Management
Manual
Digital
Traceability
Damage logged by block or row, often without serial numbers
Each defect linked to a module serial number and position
Evidence
Photos on phones and in chat groups, hard to match to modules
Geotagged, timestamped photos attached to the defect record
NCR closure
NCRs tracked through email and spreadsheets
NCRs tracked from detection to corrective action and sign-off
Replacement tracking
Hard to confirm which modules were replaced and re-tested
Replacement serial number and re-test result recorded before closure
Claim readiness
Evidence gathered from several sources when a claim comes up
Records already organized by module
How SenseHawk Helps EPCs Manage Module Breakage
SenseHawk’s TaskMapper brings module identification, field inspections, defect tracking and asset records into one digital twin of the solar site. A damaged module can be traced from the first inspection to the closed NCR, in the same solar inspection software the rest of the project uses.
TaskMapper for Inspections, NCRs and Punch Lists
Inspection forms: TaskMapper’s no-code form builder turns existing paper checklists and ITPs into digital inspection forms. Every inspection is linked to a GPS coordinate and a timestamped photo.
Offline capture: the mobile app captures data offline and syncs once back in range.
NCRs: NCRs are logged directly on the map, and teams can track their full lifecycle from detection to corrective action (CAPA) and final sign-off.
Approvals: a visual workflow builder sets up review and approval steps, so each NCR or punch list item reaches the right people before it closes.
Trend analytics: these help spot recurring defects tied to specific equipment types, material batches or installation crews.
Field teams use handheld Android devices with integrated 1D and 2D barcode scanners to record module serial numbers directly into the digital twin.
Each scan is linked to its tracker and module position.
TaskMapper structures the site as a hierarchy from module to substation, so a damaged module found during an inspection or on a thermal scan can be matched to its serial number.
Records can be reviewed in TaskMapper or exported as CSV files for client submission.
For receiving, TaskMapper’s Inventory module records incoming deliveries against serial numbers and tracks damaged items and returns.
Therm for Thermal Anomaly Detection and Remediation
Equipment Twin for Commissioning and Asset Records
The Equipment Twin is TaskMapper’s connected asset model, from module to substation:
It holds serial numbers, datasheets, warranties, IV curves, test results and maintenance history.
IV curve traces and EL images can be uploaded and mapped to the specific strings or modules they belong to.
Inspection history stays linked to the same equipment.
At handover, every asset gets a Digital Birth Certificate, a life-long record of its as-commissioned state that simplifies future warranty claims.
Best Practices to Reduce Module Breakage on Site
Inspect and photograph pallets on arrival, before unloading begins.
Store modules on level ground and stack them as the manufacturer recommends.
Carry modules according to the manufacturer’s handling guidance, and never step or kneel on them.
Follow the manufacturer’s clamping zones and torque values.
Scan serial numbers by tracker and module position, so every defect can be traced to a module.
Use the same defect categories in inspection forms across all crews.
Raise an NCR or punch list item for every confirmed damaged module, with an owner and a due date.
Review all open NCRs and punch list items before handover.
Conclusion
Module breakage can happen anywhere between delivery and commissioning, and much of it can’t be seen without testing. Visual checks, EL testing, IV curve tracing and drone thermal imaging each catch different damage at different stages. The results become useful when each finding is linked to the right module by serial number and position, then tracked through replacement, re-testing and closure. With that record in place, EPC teams can protect construction quality, resolve defects before handover and back supplier and warranty claims with evidence.
Request a SenseHawk demo to see how TaskMapper and digital asset tracking can support solar project quality management.
FAQs
What is solar module testing?
Solar module testing is the process of checking the physical condition and electrical performance of solar modules. On a construction project it includes visual inspections, EL testing, IV curve tracing, flash testing and drone thermal imaging, carried out from delivery through to commissioning.
Will a cracked solar panel still work?
Often, at least for a while. A module with cracked cells, or even cracked glass, can still produce power. Cracks can grow over time, though, reducing output and creating hot spots. Broken glass can also let in moisture and create safety risks. Cracked modules should be inspected, recorded and assessed for replacement.
How do you detect micro cracks in solar panels?
Micro cracks are usually invisible to the eye. EL testing is the most direct way to find them, because cracks show up as dark lines or areas in the image. Once a site is energized, drone thermal imaging can show hot spots that may be caused by cracked cells, which can then be confirmed in the field.
Who pays for broken modules during construction?
It depends on where the damage happened and what the contracts say. Damage in transit may fall to the supplier or logistics provider, damage during installation may fall to the installation contractor, and manufacturing defects may be covered by the module warranty. In each case, the outcome depends on records showing when, where and on which module the damage was found. That’s why recording damage at every handoff matters.
When should EL testing be done on a solar project?
EL testing is most useful at two points: on a sample of modules at receiving to check incoming quality, and more fully before commissioning to set a baseline of module condition. It can also be used to investigate modules suspected of damage during installation or after a thermal scan.
Documentation is what connects a test result to a specific module.